Uzbekistan to procure US$2.2bn in materials for Jizzakh NPP

Uzbekistan to procure US$2.2bn in materials for Jizzakh NPP
Uzbekistan to procure US$2.2bn in materials for Jizzakh NPP / Photo: Press Service of the President of Uzbekistan..

Tashkent, Uzbekistan (UzDaily.uz) — Uzbekistan will need construction materials worth US$2.2 billion for its nuclear power plant project in Jizzakh Region, President Shavkat Mirziyoyev said, according to a report on his meeting with investors and businesses in the construction and tourism sectors.

A 200-hectare special industrial zone is planned in Egizbulok to supply the project with the necessary products. The site is expected to host production facilities manufacturing 70 types of materials and products for NPP construction.

Mirziyoyev instructed officials to assess demand for import-substituting products used in major infrastructure and industrial projects. Based on the findings, a list of sectoral initiatives worth a total of US$20 billion will be prepared.

From 2027, US$200 million is planned for developing the production of new construction materials with high added value. The financing will be provided at an annual interest rate of 6%, with a two-year grace period.

In addition, companies will receive compensation covering 10% of the cost of energy-saving equipment. The subsidy will be capped at 1 billion soums.

At the same meeting, the president announced plans to build a paint and coatings plant owned by Turkish company Betek near Tashkent and instructed officials to improve the quality of domestically produced construction materials.

Uzbekistan's nuclear power plant project предусматривает the construction of two large-capacity power units and two small modular units. In September 2025, Uzatom and Rosatom agreed on the configuration of the integrated plant.

The project includes two power units equipped with Generation III+ VVER-1000 reactors and two units with RITM-200N reactors, each with a capacity of 55 MW. The plant's combined capacity is expected to exceed 2.1 GW, comprising 2 GW from the large nuclear power plant and 110 MW from the small nuclear power plant.

In October 2025, excavation work began at the site in Jizzakh Region to prepare the foundation pit for a power unit equipped with a RITM-200N reactor. Initial concrete works at the site began in March 2026.

According to Uzatom, work at that stage involved preparing the foundation of the reactor building, including waterproofing and the grounding system.

On 4 June 2026, a ceremony marking the start of construction of the integrated nuclear power plant was held in Farish district of Jizzakh Region. The first power unit was laid and the first concrete was symbolically poured.

In early September 2026, Mirziyoyev instructed officials to increase the share of locally produced goods in the NPP project to 30%. Uzatom head Azim Akhmedkhodjaev said at the time that plans were being developed to establish an industrial zone in Farish district to manufacture construction materials for the nuclear industry.

In August 2026, the president also announced the start of large-scale preparations for the construction of Uzbekistan's second nuclear power plant.

Later, on 8 September, Serbian President Aleksandar Vucic said at the Serbia-Uzbekistan business forum in Belgrade that Uzbekistan was considering involving Chinese partners in the new nuclear project.

Anvar Umarov
Anvar Umarov

Anvar Umarov is the founder and editor-in-chief of UzDaily, a leading business and news publication covering Uzbekistan and Central Asia. With over 20 years of experience in journalism, he has also worked as a PR manager for both state and private organizations, bringing a broad perspective on media, communications, and public affairs to his editorial leadership.