Tashkent, Uzbekistan (UzDaily.uz) — A new 500/220 kV substation under construction at the Navoi thermal power plant has received initial voltage on its 220 kV busbars, Uzbekistan’s Energy Ministry said.
The work is part of an investment project to build a third 650 MW combined-cycle gas turbine unit at the power plant.
Following energisation, the plant and the 300 MW Hybrid solar photovoltaic power station were connected through the new substation.
The facility is designed to strengthen electricity links between the south-western and northern parts of Uzbekistan’s unified power system. It is also expected to improve the reliability of electricity transmission through high-voltage networks and enhance the stability of the power system.
Modern equipment manufactured in Japan, China, India and South Korea is being installed to ensure the substation’s reliability and technical performance.
A consortium comprising Japan’s Mitsubishi Corporation and Mitsubishi Power Ltd is the project’s general contractor. Türkiye’s Calik Enerji is participating as a subcontractor.
At the next stage, equipment required to transmit electricity from the new combined-cycle gas turbine unit to the national power system is scheduled to be energised.
This will allow final tests and inspections of the unit to be carried out before it is gradually commissioned.