Tashkent, Uzbekistan (UzDaily.uz) — Irrigation projects involving Chinese companies in Uzbekistan have been delayed by disagreements over construction costs, Water Minister Shavkat Khamrayev said on 11 November.
He made the remarks during a government question-and-answer session in the Legislative Chamber of the Oliy Majlis.
Imomnazar Tursunov, a deputy from the People's Democratic Party of Uzbekistan, said work on several investment projects scheduled for 2026 had not yet started.
He asked about the reconstruction of irrigation infrastructure in Surkhandarya, Kashkadarya, Bukhara and Namangan regions. The US$130 million project was to be financed with the participation of the Export-Import Bank of China.
"According to the table presented, not a single soum has been disbursed for these projects," Tursunov said.
He asked the minister to explain the delays and outline how the ministry intended to ensure that foreign investment was used on schedule.
Disagreements over construction costs
Khamrayev said the ministry had initially planned to engage Chinese companies CITIC and CAMC. They were expected to begin construction using their own funds, with the costs later reimbursed through concessional Chinese loans.
However, the companies submitted proposals at prices far above the ministry's expectations.
"When we began negotiations with these companies, they submitted documents proposing to carry out the work not at prices 10% or 20% higher, but at more than twice the expected cost. They proposed starting work and gradually covering the expenses through loans," the minister said.
He said the ministry had spent more than a year trying to secure acceptable terms, but the negotiations had failed.
The government then approached the Chinese side to arrange financing through the Export-Import Bank of China under the established procedure.
According to Khamrayev, the bank takes about six months to review a project, including its assessment. A contractor is then selected from among several companies. These procedures took approximately another year.
The winning bidder offered a price 20% above the initial estimate.
Khamrayev said a tender involving three companies was subsequently held. CITIC won the tender, but its proposed price was still 20% higher than originally planned.
The ministry tried to persuade the company to lower its price, but the two sides failed to reach an agreement.
The ministry then began negotiations with another major Chinese company, Sinohydro. A further meeting with its representatives took place on the morning of 11 November, before the parliamentary session.
Khamrayev said the ministry would not accept inflated prices simply to speed up construction.
"If we agree to a high price just to complete the work sooner, the money will ultimately have to be repaid from the state budget. That is why the issue has been put on hold for now," he said.
The programme will take at least two years, according to the minister. Project documentation has already been prepared and passed the required assessment.
The canals are scheduled to be lined with concrete in 2027–2028. Khamrayev told lawmakers that the ministry intended to complete the work to a high standard and within the allocated budget.
What the presidential resolution provides
On 29 November 2024, President Shavkat Mirziyoyev signed Resolution PP-409 on the reconstruction of irrigation infrastructure in Bukhara, Namangan, Surkhandarya and Kashkadarya regions with the participation of China's Eximbank.
The document provided for two projects with a preliminary combined cost of US$220 million. US$160 million was allocated for irrigation infrastructure in Bukhara, Namangan and Surkhandarya regions, while US$60 million was earmarked for Kashkadarya region.
The Centre for the Implementation of Foreign Investment Projects in Water Management under the Ministry of Water Resources was designated as the customer. The funding was to be provided through concessional loans from China's Eximbank.
The resolution also exceptionally designated the general contractors. CITIC Construction Co. Ltd was selected for the project covering Bukhara, Namangan and Surkhandarya regions. In Kashkadarya region, the designated general contractors were CITIC Construction Co. Ltd and China CAMC Engineering Co., Ltd.
The Ministry of Investment, Industry and Trade and the Ministry of Water Resources were instructed to negotiate with China's Eximbank. They were to agree on concessional financing terms without insurance payments.
The feasibility studies were to be reviewed within one month, while draft government decisions were to be submitted within two months.
The Ministry of Water Resources, the Prosecutor General's Office and the administrations of the four regions were tasked with reducing unnecessary expenditure and monitoring the efficient use of the allocated funds.
Loan agreements with China's Eximbank were expected to be signed from 2025, following approval of the feasibility studies. The final financing amounts were to be determined based on the actual volume of work.
For the Kashkadarya project, 120 billion soums was earmarked from the local budget for 2025 to cover a 15% advance payment.