Tashkent, Uzbekistan (UzDaily.uz) — Uzbekistan’s National Urbanisation Committee has called for an assessment of Tashkent’s infrastructure capacity before considering a proposal to build a 41-storey hotel on the site of the City Palace hotel.

The committee said it was not opposed to investment or the construction of a new hotel. The main question was whether the existing infrastructure could handle the additional load generated by a high-rise building.

According to preliminary calculations, the project envisages a 41-storey building, replacing the seven floors permitted under the urban development plan. The number of hotel rooms would increase 4.5 times.

The committee also assessed the potential impact on utility and transport networks.

In particular, the reserve capacity of substations in the project area has already been exhausted, according to the committee. The regulatory limit for the load is 50%, while the actual figure is around 70%. The project could increase the load by a further 10–15% at least.

The new complex’s estimated demand for drinking water is twice the current level, the assessment said.

Existing networks would be able to provide only 65% of the required capacity, leaving a 35% shortfall. Additional infrastructure would therefore need to be developed to ensure an adequate supply.

Transport conditions have also raised concerns. According to the committee, roads along Navoi and Amir Temur streets already exceed the permitted traffic load by more than 60% during peak hours. The new facility could increase traffic pressure by a further 5–6%.

The committee also said that specific assessments would be required for the 41-storey building’s seismic resistance, fire safety, evacuation arrangements and wind loads.

The committee believes the project’s parameters must be brought into line with the urban development plan and the height of surrounding buildings before it can be considered.

The sources of additional capacity for electricity, water supply, sewerage and transport must also be identified, along with the parties responsible for building the necessary infrastructure and the implementation deadlines.

The project could then be considered in accordance with established procedures.

The committee stressed that the same approach should apply to all major projects in the capital: infrastructure capacity must be assessed first, followed by a decision on whether to grant construction approval.

Anvar Umarov
Anvar Umarov

Anvar Umarov is the founder and editor-in-chief of UzDaily, a leading business and news publication covering Uzbekistan and Central Asia. With over 20 years of experience in journalism, he has also worked as a PR manager for both state and private organizations, bringing a broad perspective on media, communications, and public affairs to his editorial leadership.