Tashkent, Uzbekistan (UzDaily.uz) — Afghanistan is nearing completion of the second stage of the Qosh Tepa Canal and preparing to begin diverting water from the Amu Darya, with earthworks 99% complete, Afghan media reported, citing the National Development Corporation (NDC).
Radio Hurriyat and TOLOnews reported on 25 November that work on this stage of the project was nearing completion.
NDC representative Nabiullah Argandival said the corporation expected to direct water from the Amu Darya into the main intake structure and main canal in the near future.
Construction of the main intake facility is continuing, he said. The corporation is monitoring the project's progress. Work is also under way on 47 bridges and water flow regulation structures.
However, the Afghan side has not specified when water deliveries will begin, the planned volumes of water withdrawal or whether agreements have been reached with countries downstream of the Amu Darya.
According to preliminary estimates cited by TOLOnews, the canal will have a capacity of around 650 cubic metres per second. This exceeds the estimate given by Uzbekistan's Water Resources Minister Shavkat Khamraev, who previously put the figure at 450–500 cubic metres per second.
The canal is expected to provide irrigation for 500,000–600,000 hectares of agricultural land. Afghanistan's authorities hope to expand cultivated areas, increase agricultural production, create jobs and reduce dependence on imports of certain food products.
Afghan economic analyst Mir Shakib Mir highlighted the importance of modernising the canal's irrigation system to use water efficiently and develop agriculture.
Wasim Safi, director general of the Afghanistan Chamber of Agriculture and Livestock, said the project would restore irrigation to land affected by drought and water shortages and improve its fertility.
Uzbekistan's position on water withdrawals
The Afghan announcement came several days after Uzbekistan's Water Resources Minister Shavkat Khamraev addressed the issue. At a news conference on 19 November, he said full-scale water withdrawal from the Amu Darya through the Qosh Tepa Canal would not begin before 2030.
Tashkent maintains an ongoing dialogue with Kabul on the use of transboundary water resources, the minister said. An Afghan delegation led by the deputy agriculture minister visited Uzbekistan in November.
Khamraev acknowledged Afghanistan's right to use Amu Darya water. He also said the two sides had agreed to sign agreements on water withdrawal volumes after construction of the canal was completed.
Asked when water withdrawals would begin, he said this would happen after construction was finished, but not before 2030.
According to preliminary Afghan calculations cited by the minister, water withdrawals could reach around 10 billion cubic metres in years with abundant water and 6 billion cubic metres in dry years.
Khamraev said these volumes were possible, but stressed that they would need to be agreed based on the river's actual flow.
The minister also said that only 200,000–250,000 hectares of the planned 500,000–600,000 hectares could be irrigated by gravity.
Supplying water to the remaining areas would require pumping stations and other infrastructure. Operating these facilities would involve significant electricity costs.
In Khamraev's assessment, Afghanistan does not yet have sufficient capacity to operate such infrastructure on the required scale. He expressed hope that the canal would become a foundation for cooperation between the two countries rather than a source of conflict.
In March 2026, Khamraev said Afghanistan's annual withdrawal of 2 billion cubic metres of water would not create critical problems for Uzbekistan.
However, he estimated that increasing withdrawals to 4 billion cubic metres could pose serious risks to the country's agriculture.
History of the canal's construction
Construction of the Qosh Tepa Canal in northern Afghanistan began in 2022. The project is designed to divert part of the Amu Darya's flow to irrigate agricultural land in the provinces of Balkh, Jawzjan and Faryab.
The canal is 285 km long and the project is divided into three stages.
The first section, measuring 108 km from the Amu Darya to Dawlatabad district in Balkh province, was completed in October 2023.
The second stage involves building a 177-km section through Jawzjan and Faryab provinces. The third stage envisages creating a distribution network to deliver water directly to agricultural land.
Afghan authorities estimated the canal's construction cost at around US$680 million, Afghanistan International reported.
However, total expenditure could reach US$1.5 billion when the development of irrigation networks is included, according to researchers' estimates.
In September 2023, President Shavkat Mirziyoyev warned that putting the canal into operation could significantly alter the water regime and balance in Central Asia.
He proposed establishing a joint working group to study the project and assess its impact on the Amu Darya's water resources.
Assessments by international researchers
In January 2026, specialists from the Norwegian Institute of International Affairs (NUPI) and the University of Missouri published a study in the journal Environmental Research: Water.
They estimated that construction of the canal could intensify water shortages and destabilise the situation in Central Asia.
To ensure sustainable water resource management and prevent potential conflicts, the researchers proposed a multilateral water-sharing agreement brokered by the international community.
In May 2026, researchers from the University of Oulu presented modelling results at the European Geosciences Union General Assembly on the potential effects of the canal's construction on Uzbekistan's Kashkadarya region.
Their calculations showed that diverting 20% of the Amu Darya's flow could reduce the region's annual available water resources by more than 1.2 billion cubic metres by 2030.
The area of irrigated land available per farmer could decrease by around 19%, while farmer employment could fall by up to 24%.
The researchers also identified risks to cotton and wheat production, the socio-economic conditions of rural communities and the potential for forced migration.
Their proposed measures included revising water management approaches, diversifying agricultural crops and supporting rural residents.
In May 2025, a research study based on satellite imagery of the canal was presented at the University of South Dakota.
According to its findings, earthworks were 70% complete by 2024. At the time, the pace of construction suggested that the canal could begin operating in 2026, two years ahead of the original schedule.
However, the study's author recorded damage to the canal wall, after which a body of water up to 10 km long formed in the desert.
The researcher estimated that problems with the strength of the earthen embankments and their vulnerability to wind erosion could delay the canal's commissioning until 2028 or later.
Jean-Paul Derouin, a researcher at the University of Reims Champagne-Ardenne, also examined the scale of the water leakage.
In an article published in the journal Remote Sensing in August 2025, he presented an analysis of Sentinel-2 satellite images.
According to his findings, the area flooded by the leak in Balkh province expanded from 450 hectares in November 2023 to 1,250 hectares in February 2024.
It reached 1,700 hectares in February 2025 and 2,400 hectares in April 2025. Satellite images from July 2025 showed that the flooded area had remained at the same level.
Concerns over project design and costs
The project's feasibility study envisaged annual water withdrawals of up to 13 billion cubic metres once the canal reached full capacity.
This figure was cited in a report by consulting firm Adroit Associates, which conducted research from 2018 to 2021 with support from the US Agency for International Development (USAID).
The work involved 20 international experts and more than 100 Afghan specialists.
In its report, published in April 2025, the company said that not all recommendations made by the feasibility study's developers had been taken into account during the project's implementation.
Experts had proposed locating the water intake facility at a higher elevation to enable gravity-fed irrigation.
However, Afghan authorities selected a different site in the Kaldar area, citing initial costs and logistical considerations.
According to Adroit Associates' calculations, the location proposed by the experts would have saved US$413 million in capital expenditure and a further US$181 million in operating costs over 10 years, compared with the option requiring water to be pumped for irrigation.
The report's authors warned that the decisions taken could affect the project's long-term efficiency.