Tashkent, Uzbekistan (UzDaily.uz) — Annual economic losses caused by traffic congestion in Tashkent are estimated at US$343 million, equivalent to 1.27% of the city's gross regional product. Jamshid Sharipov, an expert at the Development Strategy Centre, has proposed digital solutions to improve traffic management.
According to the Traffic Management Centre (TMC), around 5.2 million people travel around Tashkent every day. Traffic volumes on 81 main streets reach 770,000 vehicles a day, while their estimated combined capacity is around 400,000.
Actual traffic loads on these streets are therefore almost 1.9 times their estimated capacity. Some delays could be reduced without building new roads through better traffic light settings, coordination of roadworks and the use of digital data.
Transport growth
Uzbekistan's transport sector accounts for almost 8% of GDP and provides employment for around one million people. In recent years, the country has risen from 129th to 88th place in the World Bank's Logistics Performance Index.
Transit freight volumes reached 15.3 million tonnes in 2025. The figure is planned to increase to 18.5 million tonnes by 2030.
Major infrastructure projects are also under way. The World Bank approved US$200 million in financing to reconstruct 91 km of the M41 highway. Average traffic speeds on this section are expected to rise from 65 to around 90 km/h.
A 282-km, six-lane toll motorway between Tashkent and Samarkand is also being built. At the same time, the World Bank estimates that Uzbekistan needs to increase road capacity by around 500% by 2030 to accommodate projected freight growth.
Results from traffic light adjustments
An important step was the establishment of the Traffic Management Centre in Tashkent. Under a presidential resolution dated 4 December 2025, the centre was granted powers to manage traffic digitally, monitor roadworks and improve road safety.
According to the TMC, adaptive traffic lights are already operating at 271 intersections. A macro-level transport model of the capital has also been developed.
On Buyuk Ipak Yuli Street, synchronising 13 traffic lights using a green wave system reduced travel time towards the city centre by 29%, from 8.5 minutes to six minutes. Travel time in the opposite direction fell by 20%.
On Makhtumkuli Street, which carries around 90,000 vehicles daily, synchronising 11 traffic lights increased the capacity of the route by 12%. Travel time fell by 10%.
At the intersection of Fitrat and Heydar Aliyev streets, an analysis of traffic flows led to the green-light duration for the busiest direction being almost doubled. This was accompanied by shorter queues.
On 2 September 2026, the first day of the school year, traffic volumes increased by 30%, according to the TMC. The centre adjusted traffic light phases promptly, keeping congestion at six points.
Main causes of congestion
Sharipov identifies three factors that reduce road capacity. The first is the growth of the vehicle fleet and traffic intensity, which is outpacing infrastructure development.
On the Tashkent–Samarkand highway, actual traffic reaches 45,000 vehicles a day, compared with an estimated capacity of 32,000. This is around 41% higher than capacity. Journey times can reach six hours. Around a quarter of international highways operate under heavy traffic loads.
The second factor is the mismatch between traffic light settings and actual traffic flows. Fixed cycles do not always account for differences in traffic intensity between main and secondary streets. As a result, queues form on busy routes, while some green-light time on less congested roads is not fully used.
An INRIX study covering around 210,000 traffic lights in the United States estimated that suboptimal settings account for around 10% of all delays.
The third factor is road and engineering work that involves closing traffic lanes. According to the US Federal Highway Administration, such works account for around 10% of all delays and approximately 24% of non-recurring delays on motorways.
Similar situations have occurred in Uzbekistan at the Kamchik Pass during periods of mass returns after holidays and in Tashkent during engineering works near Yunusabad Circle.
Predictable journey times are also important for transit and tourism. Uzbekistan received 11.7 million foreign visitors in 2025, 74% of whom came from Kyrgyzstan, Tajikistan and Kazakhstan.
International experience
In Pittsburgh, a pilot implementation of the Surtrac adaptive traffic control system reduced travel times by 25.8%, waiting times by 40.6% and the number of stops by 31.3%.
Singapore operates the CRUISE system, which combines dynamic optimisation of traffic light cycles with artificial intelligence-based video analytics to detect road incidents earlier.
London uses a lane rental mechanism, under which road operators pay to occupy the busiest sections of roads, including during peak hours. Fees can reach £2,500 per day.
According to Transport for London, after the mechanism was introduced, the share of roadworks carried out outside peak hours increased from around 30% to more than 92%. Serious delays on problem sections fell by more than a third.
In the US state of Indiana, roadwork contracts took into account not only costs but also project deadlines and the number of lane closures. Repairs to the I-70 highway were completed 55 days ahead of schedule.
The Work Zone Data Exchange (WZDx) standard is used to share information about roadworks. It enables the exchange of digital data on roadwork zones, including with navigation services.
In the Netherlands, around 340 drivers took part in the Spitsmijden experiment and received between €3 and €7 for avoiding morning rush-hour journeys. The number of trips made by participants during those hours fell by around 60%. Most drivers shifted their journeys to earlier or later times.
Three areas for reform
Sharipov proposes developing the TMC into a unified digital platform for traffic management. It would bring together data from adaptive traffic lights, video surveillance, navigation services, roadworks and traffic incidents.
The first priority would be to adjust traffic light cycles according to actual traffic flows, not only on Tashkent's main roads but also on international and national highways. Particular attention should be paid to routes entering the capital and the Tashkent–Samarkand–Bukhara corridor.
The next stage could involve expanding adaptive traffic management. Once sufficient data has been collected, the proposed system would introduce algorithms to predict congestion.
The second area is the creation of a digital register of roadworks. It would cover city, national and international roads, coordinate project schedules, publish information about lane closures and share data with navigation services.
Additional measures could include differentiated fees for occupying lanes during peak hours, incentives for contractors that complete work ahead of schedule while meeting quality and safety requirements, and sensors to detect queues in roadwork zones.
The third area concerns the management of transport demand and freight flows. The expert proposes considering incentives to shift journeys away from peak hours, particularly when lanes are temporarily closed.
He also proposes improving the advance scheduling of freight vehicles arriving at the busiest border crossing points. Carriers should receive up-to-date information about the condition of transport corridors and border crossing points.
Implementation requirements
To implement the proposed solutions, the powers of the TMC over international and national roads need to be defined, or a joint mechanism with the Road Committee needs to be established.
Legislation would also need to establish lane occupation fees, maximum periods for traffic restrictions and mandatory traffic management plans for roadworks.
Sharipov also proposes signing agreements with navigation services to exchange anonymised, aggregated data while complying with personal data protection requirements.
The initial steps would include selecting pilot corridors, setting performance targets and establishing an independent assessment mechanism. Potential sources of sustainable funding could include revenue from lane occupation fees.
The programme is proposed to be implemented in stages. During the first six months, the authorities would establish baseline indicators and select pilot sections.
Over the following 6–18 months, the proposed solutions could be tested and their effectiveness assessed. Measures shown to be effective in practice would then be scaled up over the subsequent 18–36 months.
Results should be assessed based on reductions in journey times and congestion, improved transport reliability, shorter roadwork periods and fewer road accidents involving fatalities and injuries.
However, international experience should not be treated as a ready-made model for direct replication. For example, the impact of the Dutch incentive programme weakened after the payments were discontinued.
The TMC's reported reductions in travel times also require independent assessment and comparable measurements before and after the changes.
In Sharipov's view, the process should begin with accurate measurements, pilot projects and transparent assessments of their results. More effective traffic management could reduce some delays immediately, although it would not replace the construction of new roads where necessary.