Tashkent, Uzbekistan (UzDaily.uz) — Strong winds are delaying repair work on Uzbekistan's L-503 power transmission line, an outage on which has disrupted electricity supplies in the Ferghana Valley, the Energy Ministry said.
The management of JSC Uzbekistan National Electric Grids and emergency repair teams are at the site, the ministry said in an update.
Work cannot begin because of strong winds in the affected area. Repairs will start once the wind subsides and conditions allow specialists to work safely.
The ministry said the situation was under constant monitoring and promised further updates on the restoration work.
The emergency shutdown of the L-503 line occurred at 06:19 on 19 November. The 500 kV line transmits electricity from the Syrdarya Thermal Power Plant to the regions of the Ferghana Valley.
Preliminary information indicates that adverse weather conditions caused one of the transmission towers to collapse in hilly terrain with difficult access. The automatic protection system then activated, interrupting electricity transmission along the L-503 line.
The outage disrupted electricity supplies to some consumers. Temporary restrictions remain in place in parts of the Ferghana Valley until repairs are completed.
Specialists from Uzbekistan National Electric Grids are working on the restoration in cooperation with relevant organisations in Tajikistan.
Ferghana region also receives electricity through the 500 kV L-524 line, which carries power from the Novo-Angren Thermal Power Plant.