Tashkent, Uzbekistan (UzDaily.uz) — Several districts of Tashkent and Tashkent Region experienced power outages on the evening of 19 October after voltage was lost on the 110 kV Sokin-2 and Botanika-1 power transmission lines. The Tashkent City Electric Networks branch reported the incident at 19:33.
According to preliminary information, the disruptions affected parts of Kibray, Tashkent and Yunusabad districts.
Power engineers began switching consumers to backup power sources.
By 19:54, electricity supply to consumers connected to the Yunusabad, Astronomiya and Limonchi substations had been fully restored.
At 19:57, power engineers also reported that electricity supply through the L-Botanika-1 line had been secured from another source.