Uzbekistan reconstructs and modernizes power lines and transformer points

Tashkent, Uzbekistan (UzDaily.com) - Regional Electric Grids carried out works on reconstruction and modernization of power lines and transformer points.

The structure of JSC Regional Electric Grids includes 16 enterprises, including 14 enterprises of regional electric grids operating electric networks of 0.4-6-10-35-110 kV, as well as new construction, reconstruction, overhauls and maintenance of electric grid facilities households.

Last year the enterprises of REG carried out work on the reconstruction and modernization of 6,400 kilometers of power lines and 2,600 transformer points throughout the republic. As a result of the work done, the power supply to 920,000 houses in 545 mahallas improved.

As part of the implementation of the state program “Obod Qishloq”, over 2,400 kilometers of power lines and 800 transformer points were reconstructed. In addition, 2,900 kilometers of power lines and 1,600 transformer points were overhauled.

Also, as part of the implementation of the state program “Obod Mahalla”, work was carried out on the reconstruction of 234 km of power lines and 94 transformer points, capital lines were repaired 188 km long and 272 transformer points.

Along with this, practical measures have been taken to ensure comprehensive preparation of the republic's electric power sector for stable operation in the autumn-winter period of 2019/2020, including overhaul and current repair of electric networks with a length of 20,300 km and 6,800 transformer points. For the construction of external power supply facilities, under construction of affordable multi-apartment buildings in rural areas and cities of the republic, 368 km of power lines and 344 transformer points were built.

Measures have been taken to connect 720 enterprises operating in 126 free economic and small industrial zones to the power grid, in particular 160 km of power lines and 98 transformer points have been built.

In order to improve metering and control of electricity consumption over the past period, more than 2.5 million consumers were connected to an automated system for monitoring and accounting of electricity (ASKUE).

In addition, in order to increase existing capacities, as well as uninterrupted supply of electricity to consumers in 9 regions of the country, reconstruction and modernization of 16 high-voltage substations was carried out, as well as construction and installation work was carried out on 115.3 km of transmission lines with a voltage of 0.4-10 -35-110 kV.

Last year, 4 factories for the production of reinforced concrete supports were put into operation on the basis of power supply enterprises. In 2020, it is planned to put into operation another 8 plants for the production of concrete products, which will accelerate the construction of new power lines.

In order to strengthen the material and technical base and increase the level of mechanization of regional electric networks, 100 units of special equipment were delivered. In the new year, it is planned to purchase 34 automobile laboratories and 14 truck cranes.