Tashkent, Uzbekistan (UzDaily.com) -- Work on the final test of the boiler burner ignition system has been successfully completed at the plant's boiler plants.
During the test, functional testing of the ignition system, the combustion process of the burners, as well as their correct and adjusted operation were carried out.
The works were carried out in close cooperation of specialists of the GTL plant, EPC of the contractor - Enter Engineering Pte. Ltd., as well as experienced specialists of the company Welcron Kangwon Co, Ltd. (Republic of Korea) - a manufacturer of boiler plants for the GTL plant in Uzbekistan.
With the completion of the testing of the burners, the plant began work on their complete chemical cleaning. Upon completion of the chemical cleaning of the boiler plants, work will begin on their commissioning, bringing them to the design operating mode, as well as the start of steam production for the needs of the plant.
Pre-commissioning and commissioning work continues at the plant's facilities at an active pace.