Currency rates from 29/08/2025
$1 – 12482.38
UZS – 0.56%
€1 – 14540.72
UZS – 1.07%
₽1 – 155.23
UZS – 0.62%
Search
Economy 08/04/2021 Damaged power line in Surkhandarya restored
Damaged power line in Surkhandarya restored

Tashkent, Uzbekistan (UzDaily.com) -- On 4 April 2021, due to torrential rains and winds in Kumkurgan district of Surkhandarya region, two supports of the 500 kV L-508 overhead line between the Surkhan and Guzar substations collapsed.

As a result, the operation of the 500 kV power transmission line, connecting the Surkhan substation in Surkhandarya region with the Guzar substation, was disrupted.

As a result of the measures taken by the special teams of the National Electric Networks of Uzbekistan JSC to eliminate this situation, on the eve of 7 April, work was completed to restore these supports and the operation of the power transmission line was adjusted.

 

Stay up to date with the latest news
Subscribe to our telegram channel