Tashkent, Uzbekistan (UzDaily.com) -- In the first quarter of 2022, the oil and gas service ERIELL Group completed plans for the current and major workover of wells at the facilities of the customer company Sanoat Energetika Guruhi (SEG) in the first quarter of 2022.
The work plan for the current and major workover of wells (W&W) at SEG facilities was completed by 175%. The work was carried out by specialists of the ERIELL Group Well Workover Department
That is, with the plan of work on the workover of 64 wells, in fact, in the first 3 months of the year, current and major repairs of 112 wells were carried out.
In addition, in the first quarter, work was carried out with the help of coiled tubing units at 35 wells, while the plan was 22, that is, with 159% completion.
This pace of work was achieved by the Workover Department, among other things, by attracting a significant number of lifting units (PU) - if the plan provided for the use of 28 PU, then in fact 39 lifting units were involved in the work. Also, 3 coiled tubing units operated at SEG facilities during the reporting period.
Timely analysis of the situation on the current and workover of wells, the experience of the specialists of the Workover Department, the involvement, if necessary, of additional equipment, in particular lifting units - all these opportunities were used by ERIELL Group to accelerate the fulfillment of its contractual obligations.
The main goal of covering a larger number of wells with current and major repairs is to increase the production of natural gas and oil, which is necessary for the further development of the economy of the Republic of Uzbekistan, creating more and more favorable conditions for the life of the country's population.
ERIELL Group is the General Contractor at the facilities of FE LLC Sanoat Energetika Guruhi (SEG) as part of the program "Overhaul of fixed assets" in the period 2020-2023. The project covers the fields of Kashkadarya and Bukhara regions, Fergana valley.