Tashkent, Uzbekistan (UzDaily.com) -- The ERIELL Group, together with Uzbekneftegaz, continues to work to increase the production of natural gas, gas condensate and oil as part of the implementation of the “Program of measures to increase hydrocarbon production for 2017-2021.”
So, the team of drilling foreman A.Tekenov on 30 March successfully, ahead of schedule by 26 days, it drilled well No. 12 of the Uzunshor gas condensate field of the Mubarek oil and gas production department (located in the Alat district of the Bukhara region and commissioned in November 2019) with an actual depth of 2464 meters and in the range of 2463-2417.88 meters installed a filter.
After the development of this well on 4 April a significant industrial gas inflow was obtained (through a 14mm nozzle) with a daily flow rate of 468.8 thousand m3 (a table of research results is attached).