Tashkent, Uzbekistan (UzDaily.com) -- In order to ensure stable and uninterrupted supplies of natural gas to consumers of the republic and increase the production capacity of the oil and gas production departments of Uzbekneftegaz, effective work is being carried out.
According to the hydrocarbon production department, under a direct contract, 2 gas generator engines of the NK-16-18ST brand belonging to the company in the Russian JSC KMPO and one gas generator engine of the AI-336-2-8 brand in the Ukrainian JSC Motorsich "and delivered in a short time.
These 3 gas turbine engines, after overhaul and testing, were accepted by the Shurtan Oil and Gas Production Department.
Together with qualified specialists of the Department for Hydrocarbon Production and Management, without the involvement of specialists from abroad, in accordance with the instructions of the manufacturer, before the deadline, the DKS-2 stage was installed at the gas pumping unit No. 500 of the KMPO compressor station and commissioned into operation. At the same time, regular repair work was carried out on the inlet and intermediate separators of the unit and air cooling units (AVO).
As a result, an increase in the volume of gas production under management was achieved, and unnecessary costs were saved due to the involvement of specialists from abroad for installation work.
The main task of the KMPO compressor station of the BKS-2 stage is to achieve efficient natural gas production from the Shurtan and Zhanubiy Tandircha fields, as well as to increase the pressure of natural gas coming from low-pressure wells and send it to the Shurtan Head Facility.
These gas pumping units of the compressor station perform work on increasing the pressure of natural gas and transferring it to the compressor station "Bateman" without reducing the gas pressure below 18 kgf / cm2. The shutdown of one of these units will reduce the daily production of natural gas by 6.450 million cubic meters.
Also, in order to prevent gas leakage during an emergency shutdown of the gas pumping unit, a reserve unit is provided to be put into operation as soon as possible.
The compressor station KMPO of the stage "DKS-2" is located on the territory of Guzar district of Kashkadarya region and has 5 gas pumping units. The capacity is 9 billion cubic meters of natural gas per year. in 2015, the station was installed on gas-pumping units manufactured by the Russian plant KMPO JSC and put into operation.