Uzbekneftegaz: Preparations for the autumn-winter season are underway at Karshi Oil Depot
18/09/2020 20:30
Uzbekneftegaz: Preparations for the autumn-winter season are underway at Karshi Oil Depot
18/09/2020 20:30
Tashkent, Uzbekistan (UzDaily.com) -- As previously reported, in order to ensure transparency in the oil depots of Uzbekneftegaz, work has begun on the introduction of an automated system for monitoring and controlling the provision of services at the bases.
At present, on behalf of the Chairman of the Board of Uzbekneftegaz, Karshi Neftebaza LLC and its branches are carrying out large-scale work to prepare for the 2020-2021 autumn-winter season.
In particular, 4 units were cleaned in the "Karshi Oil Depot". RVS-400 cubic meters and painted 10 pcs. RGS-75 cubic meter of capacity. Also, 458 meters of technological pipes of various diameters, transition metal bridges over 12 technological pipes were repaired.
Prior to that, the unloading of oil products at the base and in the branches was carried out at railway racks, gas stations, tank warehouses and pumping stations, where the roof was in the form of a soft bitumen coating. Currently, their roof is covered with modern corrugated board.
The administrative building of Karshi Oil Terminal was heated in winter using an old boiler, which consumed a lot of fuel and energy. Now the old heating system in the building has been completely dismantled and replaced with new modern energy-efficient electric boilers.
In addition, in the Shakhrisabz, Kasan, Kitab, Yakkabog branches of Karshi Neftebaza LLC, 9 tanks and 794 meters of process pipes were cleaned of old paint and completely repainted with white enamel.
In these branches, the existing equipment of railway ramps and pumps for unloading oil products, laboratory buildings, a parking lot for gas stations and transformers were repaired. Fire-fighting shields were re-equipped. The necessary conditions have been created in the rest rooms of employees.
At the entrance to the territory of the "Guzor branch" a checkpoint building was built and commissioned.
A washroom and toilet were built for the workers. Currently, the roof of the administrative building is being replaced with a new profiled roof.